Decreto Supremo N°14/2024 (Supreme Decree 14/2024) of the Ministerio del Medio Ambiente (MMA, the Ministry of the Environment) does not have one date of entry into force, but two. Which one applies to you depends, first, on whether your project enters the Environmental Impact Assessment System (SEIA) and when it does so.
What Article 31 says
Article 31 sets the general rule: the decree enters into force 30 months after its publication in the Diario Oficial (Official Gazette). As it was published on 27 February 2026, that date is 27 August 2028.
It then adds an exception: it enters into force 18 months after publication for projects entering the SEIA from that date. For them, the date is 27 August 2027.
Article 32 repeals D.S. N°38/11 of the MMA from the entry into force of the new decree, according to those same periods. Until then, D.S. N°38/11 continues to apply.
Which period applies to you
Applying Article 31 as it is written, the reading is as follows:
| Your situation | What Article 31 says | In force from |
|---|---|---|
| Your project enters the SEIA from 27 February 2026 | Exception: 18 months after publication | 27 August 2027 |
| Your project entered the SEIA before 27 February 2026 | It is not covered by the exception: the general 30-month rule applies | 27 August 2028, in principle |
| You have a fixed source in operation with no environmental assessment | The article only distinguishes by entry into the SEIA: the general rule applies | 27 August 2028 |
Be careful with the second case: having entered the SEIA before 27 February 2026 does not settle the matter. If the construction or operation of the project takes place when D.S. N°14/2024 is already in force, the authority could ask for the project to be assessed against it as well.
What the decree does not resolve
The decree has no transitional provisions. It does not say which standard a project entering the SEIA now is assessed against, while D.S. N°38/11 still applies, when it will most probably operate under the new decree. So far, the Servicio de Evaluación Ambiental (SEA, the Environmental Assessment Service) has not given a criterion on this either.
That is the question that remains open today for a project owner: against which limits is it advisable to demonstrate compliance.
It is a habitual recommendation in our studies to calculate compliance at the receptors under both standards, so that you know from the outset how much margin there is under each.
What to define from the outset
- The date your project enters the SEIA, because it determines which of the two periods in Article 31 applies to you, and the planned dates of construction and operation, because they determine whether you could be asked to assess against the new decree.
- The limits for each receptor under D.S. N°38/11 and under D.S. N°14/2024, to see the difference between them.
- If there are receptors in rural areas, the background noise campaign: under the new decree, the level declared in the assessment or in the Resolución de Calificación Ambiental (RCA, the Environmental Approval Resolution) is the one that sets the limit. We explain this in our note on rural background noise.
To see what else the decree changes compared with D.S. N°38/11, read our note D.S. N°14/2024 (MMA): what changes under the new noise standard for fixed sources.
If your project is heading into the SEIA, see our acoustic and vibration impact studies for the SEIA. Would you rather talk it through? Book a 20-minute call: we will carry out a free preliminary diagnosis and send you a free technical proposal within 1 to 5 working days.

He leads Acústica Austral’s environmental noise and vibration studies for the SEIA across energy, port and infrastructure projects, and has contributed to reference work for Chile’s Ministry of the Environment.
Meet the team →Free resources for your project
Guide to the D.S. N°14/2024 and the acoustic checklist for entering the SEIA, in PDF. We email them to you.