A high-voltage line has no engines and no permanent works, and yet it is assessed as a noise source. For the SEA (Servicio de Evaluación Ambiental, the Environmental Assessment Service), lines and their substations are energy infrastructure, and their noise is compared with the emission standard like that of any other fixed source. What changes is how that noise is predicted and under what conditions.
Why a line makes noise
The main cause is the corona effect. When the electric field at the surface of the conductor exceeds the dielectric strength of the air, the air ionises and gives off a persistent hum or a crackling sound. The SEA calls it «audible noise». In alternating current, rain and high humidity favour it. In direct current the opposite happens: it is more likely in fair weather.
At the substation, the main source is the transformers. Their noise has its main component at twice the grid frequency, 100 Hz in the Chilean system, with harmonics. Cooling fans add broadband noise.
What the SEA requires for lines
Since 2023 the SEA has a specific criterion: «Consideraciones para la predicción y evaluación de las emisiones de ruido audible asociado al efecto corona en proyectos de transmisión eléctrica» (Considerations for predicting and assessing audible noise emissions from the corona effect in electricity transmission projects). In short, it requires:
- Predicting with recognised empirical methods and, if more than one applies, preferring the one that gives the higher exposure.
- In alternating current, calculating with rain, which is the condition of highest emission.
- Placing the source at the minimum height of the catenary.
- Measuring background noise without rain and with low wind, ideally below 5 m/s.
- Choosing receptors along the whole route, giving priority to the quietest sectors.
- Delivering noise contours every 5 dB and GIS files.
If the project includes a substation, the assessment covers the combined emission of the line and the substation, as set out in the SEA’s 2019 noise and vibration guide.
What changes with D.S. N°14/2024
D.S. N°14/2024 (MMA, the Ministry of the Environment) explicitly names transmission within energy infrastructure, and its recitals mention electricity transmission lines among the sources to which the standard applies.
In addition, its article 22 instructs the SMA (Superintendencia del Medio Ambiente, the Environmental Superintendency) to issue a specific measurement and prediction protocol for energy transmission or transport infrastructure. As of 25 October 2026 we have not found that protocol published. When it comes out, it will define how compliance is verified for these sources.
For project owners there is a point worth looking at now. In rural zones, D.S. N°14/2024 sets the limit from the rural background noise, and for projects that go through the SEIA (Sistema de Evaluación de Impacto Ambiental, the Environmental Impact Assessment System) that background noise is the one established in the assessment or in the RCA (Resolución de Calificación Ambiental, the environmental approval). A well-measured noise baseline defines the limit the project will operate under. We explain it in our note on rural background noise.
Meanwhile, D.S. N°38/11 continues to apply during the transition. The new standard enters into force on 27 August 2027 for projects entering the SEIA from its publication, and on 27 August 2028 for the rest of fixed sources. Which period applies to you is explained in our note on the entry into force of D.S. N°14/2024.
A nuance: the 100 Hz tone
Neither D.S. N°38/11 nor D.S. N°14/2024 corrects the level for tonality or low frequency: both assess in dB(A), and A-weighting strongly attenuates 100 Hz. A transformer hum can meet the limit and still be clearly perceived in a nearby home. It is not a breach, but it is a risk of annoyance worth considering when locating the equipment and designing the substation.
How we do it
We carry out noise impact studies for the SEIA: we measure the baseline, model the line and the substation together following the SEA criterion, and propose measures if the result calls for them.
Are you preparing a transmission project? Book a 20-minute call: we will carry out a free preliminary diagnosis and send you a free technical proposal within 1 to 5 working days.
See also: Noise studies for transmission lines, substations and energy storage.

He leads Acústica Austral’s environmental noise and vibration studies for the SEIA across energy, port and infrastructure projects, and has contributed to reference work for Chile’s Ministry of the Environment.
Meet the team →Free resources for your project
Guide to the D.S. N°14/2024 and the acoustic checklist for entering the SEIA, in PDF. We email them to you.