At a glance

Project (SEIA name)
AMPLIACIÓN BIOMASA CENTRO DE CULTIVO RIO REÑIHUE
Project owner (per the SEIA)
Productos del Mar Ventisqueros S.A.
Client
Environmental consultancy in charge of the DIA
Sector
Aquaculture
Location
Chaitén, Los Lagos Region (southern mouth of the Reñihue River)
Years
2022–2023
Type
Underwater noise impact study (marine fauna) for a DIA, its Addenda and the responses to the authority
Challenge
Support vessel traffic in an estuary with sea lions and cetaceans, including the blue whale.
Result
Physiological effects were ruled out; for behavioural effects, a safety zone and monitoring were defined, which the RCA adopted as commitments.
Scale
28 net pens of 40 × 40 m over 22.47 ha
Instrument and status
DIA · Approved
Environmental approval (RCA)
No. 202310001137, of 6 December 2023

The challenge

The project expands a salmon farming site at the southern mouth of the Reñihue River, in Chaitén: it goes from 69 circular net pens to 28 square pens of 40 × 40 m, over 22.47 ha. All supplies and harvests arrive by sea, and South American sea lions and blue whales were recorded in the estuary. During the assessment, the authority asked for the analysis to be extended to other species (southern river otter, marine otter, Chilean dolphin, Peale’s dolphin, blue whale and orca) and for the measures to be specified.

What we did

  • We identified the sites of interest for pinnipeds and cetaceans from the project’s marine fauna surveys and the literature.
  • We modelled underwater noise propagation during construction, operation and closure: vessel and pontoon traffic, in one-third octave bands.
  • We assessed physiological effects with the NMFS technical guidance (2018) and behavioural effects with Southall et al. (2007), following the SEA noise and vibration guide (2019).
  • We updated the study for the Addendum and the Complementary Addendum, and answered the observations of two 2022 ICSARA reports.

The result

  • We ruled out physiological effects in all phases. For the behavioural effects that vessel traffic could cause, we proposed a safety zone: maximum speed of 6.5 knots for larger vessels, 7.5 for smaller ones and 4.5 for auxiliary boats, a 100 m distance upon a sighting, and speed control with POSAT.
  • We also proposed annual 24-hour underwater noise monitoring at two points, one for pinnipeds and one for cetaceans. With these measures, the potential noise impact on marine fauna was ruled out, and the RCA adopted the safety zone and the monitoring as project commitments.
  • The DIA was approved (RCA No. 202310001137, of 6 December 2023).

Services used in this project

Documentation

Public record of the project in the SEIA (Chile’s Environmental Impact Assessment System).