Noise and vibration for the DIA of an energy storage system in Bulnes

At a glance
- Project (SEIA name)
- Proyecto Sistema de Almacenamiento BESS Lucero y Línea de Transmisión 66 kV
- Project owner (per the SEIA)
- África Solar SpA
- Client
- Environmental consultancy in charge of the DIA
- Sector
- Energy: storage and transmission
- Location
- Rural area of Bulnes, Diguillín Province, Ñuble Region
- Years
- 2025
- Type
- Noise and vibration impact studies for a DIA, and responses to the authority's observations (ICSARA)
- Challenge
- Works and equipment in a rural setting with background noise of 28 to 35 dBA at night.
- Result
- With machinery restrictions and noise barriers, compliance with D.S. No. 38/11 at all receptors and in all phases.
- Scale
- 95 MW of power and 340 MWh of maximum capacity, in 76 battery containers362 m, 66 kV line
- Instrument and status
- DIA · Approved
- Environmental approval (RCA)
- No. 20261600131, of 30 June 2026
The challenge
A battery energy storage system (BESS), with a substation and a line connecting to the existing Lucero substation. In this rural setting background noise is low: at night, 28 to 35 dBA were measured at the dwellings. That is why construction and operating equipment can be noticed from further away.
What we did
- We measured background noise, by day and by night, at dwellings and fauna sites.
- We modelled construction, operation and closure. The area of influence reached 1,033 m for stationary sources.
- We assessed the five protection objects of Article 11 of Law 19,300: population health with D.S. No. 38/11 of the MMA, ways of life and customs with Royal Decree 1367/2007 (the Spanish reference standard), and native fauna, tourism value and cultural heritage. We also reviewed the synergistic effect with nearby projects.
- In parallel we carried out the vibration study and prepared the responses to the authority’s observations (ICSARA).
The result
- Without measures, construction and closure reached 70 dBA at the nearest dwellings and the limits of D.S. No. 38/11 were exceeded.
- We proposed restricting machinery and using mobile noise barriers during construction and closure, and fixed barriers during operation.
- With these measures, the project complies with the standard at all receptors and in all its phases. We left a monitoring plan for construction and operation.
- The DIA was approved (RCA No. 20261600131, of 30 June 2026).
Services used in this project
Documentation
Public record of the project in the SEIA (Chile’s Environmental Impact Assessment System).
Project and project owner as stated in the public SEIA record. Acústica Austral prepared the study described here; this case does not represent the views of the project owner.